Could Labor Shortages Slow the Data Center Construction Boom?16 min read

by | Oct 29, 2026 | Blog

The last couple of years have witnessed trillions of dollars in announced investments in new data centers. Nvidia GPU production can’t keep up with demand. Components like transformers are experiencing extended lead times. It appears that just about everything connected with AI and AI data centers is experiencing unprecedented demand.

The same holds true for the workforce. Mechanical, electrical, and plumbing (MEP) work, in particular, has become a serious bottleneck for data center projects. These workers are critical to building the cooling systems, power infrastructure, and plumbing and cabling needed by new data centers. Yet there is a 20–50% gap between planned and actual MEP output across the data center sector. This could mean serious delays in bringing large AI facilities online.

Researchers from construction AI analytics firm Buildots looked across 25 million square feet of global data center projects to see how MEP trades are performing against plan. While all MEP trades were found to be operating below the required pace of data center construction, some are performing better than others. HVAC work is progressing at 76.9% of the planned pace, electrical at 59.4%, and water systems at 44.9%.

The shortfall in output can be explained in several ways:

The rush to build AI data centers in record time is leading to an overestimation of the amount of work tradespeople can realistically complete within a given timeframe.

A serious shortage of qualified MEP workers is holding back project timelines.

The unprecedented scale and pace of data center construction are creating challenges around project coordination, scheduling, and resource management.

The report also discovered that these MEP trades sometimes work three to five times faster than their typical weekly average. This suggests that worker capability alone may not be the primary issue. Under the right conditions, crews can make significant progress. The gap may instead point to site-level challenges limiting consistent performance. Material shortages, poor coordination, and inadequate scheduling can leave untapped capacity on many projects.

Hurry Up and Wait

It appears, then, that the rush to build AI data centers in record time and record numbers is running into organizational and logistical challenges. It is one thing to get a project approved and workers and materials onsite, and quite another to coordinate those resources effectively to meet construction targets.

With so many planned data center projects facing delays due to permitting, community opposition, interconnection challenges, financing, and other obstacles, more attention could be paid to improving the efficiency of projects that have already been approved and are under construction.

Data center developers are accustomed to managing the construction of traditional facilities. Add AI into the mix, dramatically increase the scale of projects, and introduce aggressive timelines from hyperscalers like Google, Meta, Amazon, and Microsoft, and the challenges become considerably more complex. The result can be a familiar phenomenon: hurry up and wait. Workers and materials may be onsite, but coordination issues and logistical constraints can prevent construction from progressing as quickly as planned.

The industry is building data centers at a scale and pace that would have been difficult to imagine just a few years ago. Those involved are learning and adapting as they go. While expanding the skilled workforce remains important, improving coordination, scheduling, and resource utilization could be equally critical to accelerating construction.

Expect more attention to be paid to the efficiency of projects already underway, as these facilities represent some of the most immediate opportunities to bring additional AI computing capacity online.

The industry's easiest to install containment!

AisleLok® solutions are designed to enhance airflow management,
improve cooling efficiency and reduce energy costs.

The industry's easiest to install containment!

AisleLok® solutions are designed to enhance airflow management,
improve cooling efficiency and reduce energy costs.

Drew Robb

Drew Robb

Writing and Editing Consultant and Contractor

Drew Robb has been a full-time professional writer and editor for more than twenty years. He currently works freelance for a number of IT publications, including eSecurity Planet and CIO Insight. He is also the editor-in-chief of an international engineering magazine.

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Subscribe to the Upsite Blog

Follow Upsite

Archives

Cooling Capacity Factor (CCF) Reveals Data Center Savings

Learn the importance of calculating your computer room’s CCF by downloading our free Cooling Capacity Factor white paper.

Pin It on Pinterest